MANUFACTURING FACILITY RENOVATIONS

LOCATION: NEW JERSEY

CLIENT: PHARMACEUTICAL

MARKET SECTOR: SCI-TECH 


THE OPPORTUNITY

A pharmaceutical client was looking to carry out necessary plant modifications of existing pre-engineered cleanrooms to accommodate a new QC lab and Waste Storage Room.

 

 THE CHALLENGE

The challenge was to minimize costs of installation of the lab by re-using as much of the existing pre-engineered components as possible in the new layout.

 


THE PS&S SOLUTION

PS&S worked with the lab users and the facility engineering team to establish a program, develop conceptual layouts and develop construction documents for the project. 

PS&S worked with the facility engineering team to review existing chemical storage requirements, review chemical transfer operations and develop a conceptual layout that enabled the facility to secure CAR (Capital Appropriations) for the project.