WARREN TOWNSHIP SEWERAGE AUTHORITY
Stage I/II and IV Sewer Service Area Rehabilitation Projects
LOCATION: WARREN, NJ
CLIENT: WARREN TOWNSHIP SEWERAGE AUTHORITY
MARKET SECTOR: PUBLIC
 
        
        
      
           
        
        
      
           
        
        
      
           
        
        
      
    THE OPPORTUNITY
Over the past several years, the WTSA has had increasing levels of Infiltration and Inflow (I&I) in their sewer collection systems. These extraneous flows reduce the available capacity in the collections systems and plants, cause maintenance and operational issues and are a detriment to the long term compliance with their NJPDES permits.
THE CHALLENGE
PS&S needed to investigate, find, and reduce average and peak flows to their wastewater treatment plants to ensure long term compliance with their NJPDES permits and provide for consistent and continual capacity in their collection systems. 
  
 
  Implementation  of  the  investigate  and  remediation  was  difficult  in  easements,  along  streams,  and  other  tough  to  reach  locations.  These  areas  were  able  to  be  completed  through  detailed  coordination  between  the  Authority,  engineers  PS&S  and  the  pipe  and  manhole rehabilitation Contractors. In addition, due to COVID restrictions/impacts many residents in both SSA’s were home during the day while work was being performed which required a greater level of public relations coordination and outreach.
THE PS&S SOLUTION
The program ultimately achieved the stated goals through the performance of flow studies in  several  sewer  service  areas,  GIS  mapping  locating  assets,  smoke  testing  and  the  CCTV’ing of approximately 59,500 linear feet (LF) of sewer lines in the Stage I/II SSA and 87,306 LF of sewer lines in the Stage IV SSA. In addition, the WTSA implemented a new technology Focused Electronic Leak Location (FELL) testing on 9,440 LF of the collection system located in hard-to-reach easement locations. The WTSA also invested in purchasing temporary flow meters for deployment though-out the SSA to monitor wet weather flows and determine sub basins in need of further investigation or rehabilitation work. Once all the data was collected and reviewed to confirm and locate sources of I&I the remediation and removal of the I&I was performed under the following capital improvement projects:  
  
Contract 60 – Stage I/II SSA Collection System Rehabilitation Project: This project entailed the  rehabilitation  of  sewers  and  manholes  in  the  Stage  I/II  SSA  including  approximately  11,500 LF of 8” Cured In Place Pipe (CIPP) Lining, 1,000 LF of 12” CIPP Lining, 16 lateral connection  repairs,  161  LF  of  manhole  lining  rehabilitation  and  general  sewer  collection  maintenance work.
 
Contract 61- Stage IV SSA Collection System Rehabilitation Project: This project entailed the  rehabilitation  of  sewers  and  manholes  in  the  Stage  IV  SSA,  including  approximately  16,100  LF  of  8”  Cured  In  Place  Pipe  (CIPP)  Lining,  800  LF  of  12”  CIPP  Lining,  12  lateral  connection repairs, 300 LF of manhole lining rehabilitation and general sewer collection maintenance work.
  
Both projects were to reduce wet weather peak I&I flows to the Stage I/II WWTF and Stage IV WWTF and maintain the long term “health” of the collection systems. In addition, both projects were scoped to be trenchless cured-in-place (CIP) lining projects which caused minimal disruption during construction to residences and no excavation in neighborhoods was required.
   
   The  WTSA  received  the  Association  of  Environmental  Authorities  (AEA)  2021  Best  Management Practices Award for these projects.
