WARREN TOWNSHIP SEWERAGE AUTHORITY
Summerhill Pump Station Upgrade
LOCATION: WARREN, NJ
CLIENT: WARREN TOWNSHIP SEWERAGE AUTHORITY
MARKET SECTOR: PUBLIC
 
        
        
      
           
        
        
      
           
        
        
      
           
        
        
      
    THE OPPORTUNITY
The existing 65 gpm Summerhill Pump Station was at the end of its useful life and beyond rehabilitation. The pump station served a quiet residential area in the Authorities Stage 1/2 Service Area, providing sanitary service to approximately 16 homes.
THE CHALLENGE
The site was very small and constrained by surrounding properties which made decommissioning and installing the new pump station and equipment difficult. The existing pump station needed to be on bypass and have continuous operation during the new construction. In addition, the existing backup generator needed to be relocated while maintaining operations.
THE PS&S SOLUTION
PS&S  performed  a  detailed  design,  site  survey,  and  created  Contract  Specifications  for  the new wet well, valve vault, controls, transfer switch, pumps, and replacement of existing JCP&L  transformer.  The  project  was  publicly  bid  in  accordance  with  NJ  local  public  contract law and successfully completed.
  
  Through  careful  Contractor  coordination  and  scheduling  the  project  was  successfully  completed  on  the  small  project  site  with  minimal  disturbance  to  the  surrounding  neighborhood all while maintaining operations.